•Site Engineer : Aug 2011- Feb 2012

• Project Control Engineer : March 2012- June 2013

Involve in:

  • Site Engineer:
    • Helping QC reporting for Stations.
  • Project Control Engineer:
    • QC Engineer of Stations O7, P7, Q7, U7 and W7
    • Construction Schedule Control for Stations N7-W7.
    • Implementing ISO 9001 and ISO 14000 Guidelines for System Integration of Station Construction.

Contract:

SEPASAD Construction Group; Ranked 1st among Iranian Based Construction Co. in M.A.K.E. (Most Admired Knowledge Enterprise; It has a global community of Knowledge-driven organizations dedicated to networking, benchmarking and sharing best practices leading to superior performance).

• EPC of Line 7 of Tehran Urban and Suburban Railway Co. (Tehran Metro)

Contract Cost: 1760 million USD

A 28 km EPB-TBM tunnel (SELI, Italy and Herrenknecht, Germany) and 25 underground stations.


• Site Engineer: Sept 2009 - May 2011

• Project Control Engineer: July 2013- present

SAZBON Consulting Co., Line 4 and Line 3 of Tehran Metro

Involve in:

  • Site Engineer, part time:
    • Cooperating in Analysis and design of Karun 3 Hydropower cavern
  • Project Control Engineer:
    • Contract evaluation
    • Bid document preparation
    • Project Control of Design and Engineering Department

    • University Activities (SUT):

      - Member of Editorial Board, Sharif Civil Engr. Magazine, 2009-2010

      - Team Leader in Technical Field Trips, 2009-2011